Z043 - Translational Science Center is a 68,000-square-foot office building at 4875 Broadway, Sacramento in Sacramento, California, built in 1989. In its 2020 California benchmarking disclosure it reported a site energy-use intensity of 5.2 kBtu/ft² and 24 tCO₂e of greenhouse-gas emissions.
AB 802 (Public Resources Code §25402.10) · reporting year 2020
Benchmarking record
| Field | Value |
|---|---|
| ENERGY STAR score | — |
| Site EUI | 5.2 kBtu/ft² |
| Source EUI | — |
| GHG emissions | 24 tCO₂e |
| GHG intensity | 0.3 kgCO₂e/ft² |
| Electricity | 104,322 kWh |
| Natural gas | 2 therms |
| Gross floor area | 68,000 sq ft |
| Source record | california:3081371:2020 |
Compliance context
AB 802 (Public Resources Code §25402.10)
AB 802 requires every California commercial building over 50,000 sq ft to report energy use to the CEC annually; the CEC publicly discloses the results statewide.
Ownership
No owning organisation shown. Names of private individuals in the disclosure are not published here.
Own or manage this building? Claim it to correct the record and get compliance alerts.
Location
- Address
- 4875 Broadway, Sacramento
- City
- California
- State
- California
- ZIP
- 95820
- Coordinates
- 38.54724, -121.45100
Within ~1 km
Nearby benchmarked buildings
- Z073 - Central Utility Plantscore —
Energy/Power Station · 3,426,018 sq ft
- Z010 - Ses Pavillionscore —
Hospital (General Medical & Surgical) · 560,684 sq ft
Medical Office · 439,467 sq ft
Office · 335,427 sq ft
- Shriners Hospital For Childrenscore 23
Hospital (General Medical & Surgical) · 300,000 sq ft
- Z072 - Broadway Buildingscore 82
Office · 109,570 sq ft
See also: most efficient in California · biggest emitters
How does Z043 - Translational Science Center compare with other office buildings in California?
The latest disclosures cover 6,214 office buildings in California, out of 40,029 buildings citywide. Its site EUI of 5.2 kBtu/ft² is about 91% below the average of 56.4 kBtu/ft² — it uses less energy per square foot than the typical building in that group. Its emissions intensity of 0.3 kgCO₂e/ft² is about 92% below the group average of 3.6 kgCO₂e/ft².
At 68,000 sq ft, it is about 55% below the average floor area of 151,937 sq ft for those buildings. It was built in 1989, 4 years later than the group's average year built (1985). Across all 24 jurisdictions BuildingCensus covers, the 15,264 office buildings average an ENERGY STAR score of 73 and a site EUI of 59.3 kBtu/ft².
What does a site EUI of 5.2 kBtu/ft² mean?
Site energy-use intensity (EUI) is the energy a building uses on site in a year divided by its floor area, in thousand Btu per square foot — lower is more efficient. Z043 - Translational Science Center's 5.2 kBtu/ft² across 68,000 sq ft works out to about 0.4 billion Btu (104 MWh-equivalent) in 2020. The disclosure also reports 104,322 kWh of electricity and 2 therms of natural gas for the year.
Which law requires Z043 - Translational Science Center to report its energy use?
Z043 - Translational Science Center reports under AB 802 (Public Resources Code §25402.10), the legal basis of California's Building Energy Benchmarking Program (statewide), which publishes each covered building's annual benchmarking results. The record shown here is the report-year 2020 disclosure (source record california:3081371:2020). AB 802 requires every California commercial building over 50,000 sq ft to report energy use to the CEC annually; the CEC publicly discloses the results statewide.
More office buildings in California
- Redlands· 67,988 sq ft · score 99 (A)
- La Jolla Corporate Center· 67,970 sq ft · EUI 41.8 kBtu/ft²
- Auburn Regional Center - B2 Shops And Labs· 67,953 sq ft · score 99 (A)
- 80 Technology Dr.· 67,940 sq ft · EUI 35.2 kBtu/ft²
- 845-855 Embedded Way· 67,912 sq ft · EUI 163.4 kBtu/ft²
- Balboa Corporate Center· 67,866 sq ft · EUI 9.4 kBtu/ft²
- Office buildings in California· 6,214 benchmarked
- All California benchmarked buildings· AB 802 (Public Resources Code §25402.10)
- Most efficient large buildings in California
- Least efficient large buildings in California
- Biggest emitters in California
Frequently asked questions
What is Z043 - Translational Science Center's energy grade?
Z043 - Translational Science Center did not report an ENERGY STAR score in its 2020 disclosure, but its site energy-use intensity was 5.2 kBtu/ft².
How much energy does Z043 - Translational Science Center use?
Its 2020 site energy-use intensity was 5.2 kBtu/ft² across 68,000 sq ft, including 104,322 kWh of electricity and 2 therms of natural gas.
What are Z043 - Translational Science Center's carbon emissions?
Z043 - Translational Science Center reported 24 tCO₂e of greenhouse-gas emissions (0.3 kgCO₂e/ft²) for 2020.
Where is Z043 - Translational Science Center?
Z043 - Translational Science Center is at 4875 Broadway, Sacramento, in Sacramento, California 95820. Its coordinates are 38.54724, -121.45100 (latitude, longitude), as published in the Building Energy Benchmarking Program (statewide) file.
How big is Z043 - Translational Science Center and when was it built?
Z043 - Translational Science Center has 68,000 sq ft of gross floor area, as reported in its 2020 disclosure. The disclosure lists 1989 as its year built. It is classed as office.
Is Z043 - Translational Science Center covered by AB 802 (Public Resources Code §25402.10)?
Yes — it appears in the 2020 Building Energy Benchmarking Program (statewide) disclosure, which lists the buildings reporting under AB 802 (Public Resources Code §25402.10).
Working with California building benchmarking records? Pro adds alerts, change history and CSV export ($49/mo); Enterprise adds full national files, the API and an MCP server for AI tools.
About this data
Source: Building Energy Benchmarking Program (statewide) (AB 802 (Public Resources Code §25402.10)), as published July 9, 2026. See the methodology for how records are matched, cleaned and scored.