At a glance

Far East Center - Building 1 is a 32,584-square-foot restaurant building at 333 S. Federal Blvd in Denver, Colorado, built in 1987. In its 2023 Denver benchmarking disclosure it reported a site energy-use intensity of 191.8 kBtu/ft² and 510 tCO₂e of greenhouse-gas emissions.

ENERGY STAR score
—
not reported · 2023
Site EUI
191.8
kBtu/ft²
GHG emissions
510
tCO₂e
GHG intensity
—
kgCO₂e/ft²
Floor area
32,584
sq ft
Year built
1987
vintage

Energize Denver Building Performance Policy · reporting year 2023

Benchmarking record

FieldValue
ENERGY STAR score—
Site EUI191.8 kBtu/ft²
Source EUI—
GHG emissions510 tCO₂e
GHG intensity—
Electricity511,369 kWh
Natural gas45,064 therms
Gross floor area32,584 sq ft
Source recorddenver:3592:2023

The disclosure history

Year over year

YearScoreΔSite EUIGHG emissions
2023latest—191.8 kBtu/ft²510 tCO₂e
2022—200.6 kBtu/ft²548 tCO₂e
2021—207.6 kBtu/ft²581 tCO₂e

Compliance context

Energize Denver Building Performance Policy

Energize Denver sets energy-use (EUI) targets for buildings of 25,000+ sq ft — for most buildings an interim target in 2028 and a final target in 2032 — with civil penalties of roughly $0.15–0.35 per kBtu over target for non-compliance.

Program details →

Ownership

No owning organisation shown. Names of private individuals in the disclosure are not published here.

Own or manage this building? Claim it to correct the record and get compliance alerts.

Location

Address
333 S. Federal Blvd
City
Denver
State
Colorado
ZIP
80219

Within ~1 km

Nearby benchmarked buildings

This source publishes no coordinates, so nearby buildings can't be resolved yet.

See also: most efficient in Denver · biggest emitters

How does Far East Center - Building 1 compare with other restaurant buildings in Denver?

The latest disclosures cover 5 restaurant buildings in Denver, out of 3,287 buildings citywide. Its site EUI of 191.8 kBtu/ft² is about 23% above the average of 156.4 kBtu/ft² — it uses more energy per square foot than the typical building in that group.

At 32,584 sq ft, it is about 19% below the average floor area of 40,214 sq ft for those buildings. It was built in 1987, 43 years later than the group's average year built (1944).

How has Far East Center - Building 1's energy performance changed over time?

BuildingCensus holds 3 Denver disclosures for Far East Center - Building 1, covering report years 2021–2023. Site EUI moved from 207.6 kBtu/ft² (2021) to 191.8 kBtu/ft² (2023), a 8% decrease. Reported emissions went from 581 tCO₂e to 510 tCO₂e over the same span (down 12%).

What does a site EUI of 191.8 kBtu/ft² mean?

Site energy-use intensity (EUI) is the energy a building uses on site in a year divided by its floor area, in thousand Btu per square foot — lower is more efficient. Far East Center - Building 1's 191.8 kBtu/ft² across 32,584 sq ft works out to about 6.2 billion Btu (1,832 MWh-equivalent) in 2023. The disclosure also reports 511,369 kWh of electricity and 45,064 therms of natural gas for the year.

Which law requires Far East Center - Building 1 to report its energy use?

Far East Center - Building 1 reports under the Energize Denver Building Performance Policy, the legal basis of Denver's Energize Denver Benchmarking program, which publishes each covered building's annual benchmarking results. The record shown here is the report-year 2023 disclosure (source record denver:3592:2023). Energize Denver sets energy-use (EUI) targets for buildings of 25,000+ sq ft — for most buildings an interim target in 2028 and a final target in 2032 — with civil penalties of roughly $0.15–0.35 per kBtu over target for non-compliance.

More restaurant buildings in Denver

Frequently asked questions

What is Far East Center - Building 1's energy grade?

Far East Center - Building 1 did not report an ENERGY STAR score in its 2023 disclosure, but its site energy-use intensity was 191.8 kBtu/ft².

How much energy does Far East Center - Building 1 use?

Its 2023 site energy-use intensity was 191.8 kBtu/ft² across 32,584 sq ft, including 511,369 kWh of electricity and 45,064 therms of natural gas.

What are Far East Center - Building 1's carbon emissions?

Far East Center - Building 1 reported 510 tCO₂e of greenhouse-gas emissions for 2023.

Where is Far East Center - Building 1?

Far East Center - Building 1 is at 333 S. Federal Blvd, in Denver, Colorado 80219.

How big is Far East Center - Building 1 and when was it built?

Far East Center - Building 1 has 32,584 sq ft of gross floor area, as reported in its 2023 disclosure. The disclosure lists 1987 as its year built. It is classed as restaurant.

Is Far East Center - Building 1 covered by the Energize Denver Building Performance Policy?

Yes — it appears in the 2023 Energize Denver Benchmarking disclosure, which lists the buildings reporting under the Energize Denver Building Performance Policy.

Working with Denver building benchmarking records? Pro adds alerts, change history and CSV export ($49/mo); Enterprise adds full national files, the API and an MCP server for AI tools.

About this data

Source: Energize Denver Benchmarking (Energize Denver Building Performance Policy), as published July 9, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: BuildingCensus, “Far East Center - Building 1, Denver, Colorado — 2023 benchmarking disclosure”, https://buildingcensus.com/buildings/denver/far-east-center-building-1-9862fd71 (data as of July 9, 2026).