AECOM College, Laboratory Spaces and Weiler Campus
Laboratory in New York City, NY · 1300 Morris Park Avenue · 10461
At a glance
AECOM College, Laboratory Spaces and Weiler Campus is a 2,173,486-square-foot laboratory building at 1300 Morris Park Avenue in New York City, New York, built in 1949. In its 2024 New York City benchmarking disclosure it reported a site energy-use intensity of 390.8 kBtu/ft² and 59,462 tCO₂e of greenhouse-gas emissions.
Local Law 84 (LL84) · reporting year 2024
Benchmarking record
| Field | Value |
|---|---|
| ENERGY STAR score | — |
| Site EUI | 390.8 kBtu/ft² |
| Source EUI | 594.9 kBtu/ft² |
| GHG emissions | 59,462 tCO₂e |
| GHG intensity | 27.4 kgCO₂e/ft² |
| Electricity | 67,228,449 kWh |
| Natural gas | 6,138,191 therms |
| Gross floor area | 2,173,486 sq ft |
| Source record | nyc:36314550:2024 |
Compliance context
Local Law 84 (LL84)
Under Local Law 97, buildings over 25,000 sq ft face carbon caps with fines of $268 per metric ton of CO₂e over the limit, phasing in from 2024.
Ownership
No owning organisation shown. Names of private individuals in the disclosure are not published here.
Own or manage this building? Claim it to correct the record and get compliance alerts.
Location
- Address
- 1300 Morris Park Avenue
- City
- New York City
- State
- New York
- ZIP
- 10461
- Coordinates
- 40.85118, -73.84482
Within ~1 km
Nearby benchmarked buildings
- Benchmarking Group - 23score 94
Hospital (General Medical & Surgical) · 1,654,909 sq ft
Parking · 1,430,605 sq ft
Laboratory · 911,540 sq ft
- 1925 Eastchester Rdscore 74
Multifamily Housing · 754,120 sq ft
- 1250 Waters Placescore —
Office · 743,316 sq ft
Hospital (General Medical & Surgical) · 716,550 sq ft
See also: most efficient in New York City · biggest emitters
How does AECOM College, Laboratory Spaces and Weiler Campus compare with other laboratory buildings in New York City?
The latest disclosures cover 90 laboratory buildings in New York City, out of 48,310 buildings citywide. Its site EUI of 390.8 kBtu/ft² is roughly in line with the average of 409.2 kBtu/ft² — it uses less energy per square foot than the typical building in that group. Its emissions intensity of 27.4 kgCO₂e/ft² is roughly in line with the group average of 28.8 kgCO₂e/ft².
At 2,173,486 sq ft, it is about 641% above the average floor area of 293,236 sq ft for those buildings. It was built in 1949, 16 years earlier than the group's average year built (1966). Across all 24 jurisdictions BuildingCensus covers, the 795 laboratory buildings average an ENERGY STAR score of 29 and a site EUI of 231.7 kBtu/ft².
What does a site EUI of 390.8 kBtu/ft² mean?
Site energy-use intensity (EUI) is the energy a building uses on site in a year divided by its floor area, in thousand Btu per square foot — lower is more efficient. AECOM College, Laboratory Spaces and Weiler Campus's 390.8 kBtu/ft² across 2,173,486 sq ft works out to about 849.4 billion Btu (248,934 MWh-equivalent) in 2024. Its source EUI of 594.9 kBtu/ft² also counts the energy lost generating and delivering that power, which is why it is higher. The disclosure also reports 67,228,449 kWh of electricity and 6,138,191 therms of natural gas for the year.
Which law requires AECOM College, Laboratory Spaces and Weiler Campus to report its energy use?
AECOM College, Laboratory Spaces and Weiler Campus reports under Local Law 84 (LL84), the legal basis of New York City's Energy and Water Data Disclosure program, which publishes each covered building's annual benchmarking results. The record shown here is the report-year 2024 disclosure (source record nyc:36314550:2024). Under Local Law 97, buildings over 25,000 sq ft face carbon caps with fines of $268 per metric ton of CO₂e over the limit, phasing in from 2024.
More laboratory buildings in New York City
- Weill Cornell Medicine campus· 1,862,814 sq ft
- Rockefeller University Main Campus· 1,546,119 sq ft
- Annenberg· 1,119,997 sq ft
- 1250-1300 Morris Park Avenue (South Campus, Lot 1)· 911,540 sq ft · EUI 558.5 kBtu/ft²
- Alexandria Center for Life Science· 795,486 sq ft · EUI 257.8 kBtu/ft²
- Zuckerman Research Center - Part MSK Campus· 728,239 sq ft · EUI 356.7 kBtu/ft²
- Laboratory buildings in New York City· 90 benchmarked
- All New York City benchmarked buildings· Local Law 84 (LL84)
- Most efficient large buildings in New York City
- Least efficient large buildings in New York City
- Biggest emitters in New York City
Frequently asked questions
What is AECOM College, Laboratory Spaces and Weiler Campus's energy grade?
AECOM College, Laboratory Spaces and Weiler Campus did not report an ENERGY STAR score in its 2024 disclosure, but its site energy-use intensity was 390.8 kBtu/ft².
How much energy does AECOM College, Laboratory Spaces and Weiler Campus use?
Its 2024 site energy-use intensity was 390.8 kBtu/ft² (594.9 kBtu/ft² source) across 2,173,486 sq ft, including 67,228,449 kWh of electricity and 6,138,191 therms of natural gas.
What are AECOM College, Laboratory Spaces and Weiler Campus's carbon emissions?
AECOM College, Laboratory Spaces and Weiler Campus reported 59,462 tCO₂e of greenhouse-gas emissions (27.4 kgCO₂e/ft²) for 2024.
Where is AECOM College, Laboratory Spaces and Weiler Campus?
AECOM College, Laboratory Spaces and Weiler Campus is at 1300 Morris Park Avenue, in New York City, New York 10461. Its coordinates are 40.85118, -73.84482 (latitude, longitude), as published in the Energy and Water Data Disclosure file.
How big is AECOM College, Laboratory Spaces and Weiler Campus and when was it built?
AECOM College, Laboratory Spaces and Weiler Campus has 2,173,486 sq ft of gross floor area, as reported in its 2024 disclosure. The disclosure lists 1949 as its year built. It is classed as laboratory.
Is AECOM College, Laboratory Spaces and Weiler Campus covered by Local Law 84 (LL84)?
Yes — it appears in the 2024 Energy and Water Data Disclosure disclosure, which lists the buildings reporting under Local Law 84 (LL84).
Working with New York City building benchmarking records? Pro adds alerts, change history and CSV export ($49/mo); Enterprise adds full national files, the API and an MCP server for AI tools.
About this data
Source: Energy and Water Data Disclosure (Local Law 84 (LL84)), as published October 2, 2026. See the methodology for how records are matched, cleaned and scored.
Cite as: BuildingCensus, “AECOM College, Laboratory Spaces and Weiler Campus, New York City, New York — 2024 benchmarking disclosure”, https://buildingcensus.com/buildings/new-york-city/aecom-college-laboratory-spaces-and-weiler-campus-2a09ff60 (data as of October 2, 2026).